Shoreham (Brighton City) Airport Sussex
28th August

Development Proposals

Against this complex background, the owning authorities therefore decided to obtain appropriate professional advice on the potential to develop the airfield.

A team led by Drivers Jonas, supported by The Aviation and Travel Consultancy and Mott MacDonald were appointed and have concentrated on the technical and financial feasibility of several potential development options. To date, they have advised on a number of key areas:

  • 1. The potential demand for growth of aircraft movements and for the introduction and development of commercial air services at Shoreham
  • 2. The technical requirements and constraints placed on such services by the existing runway lengths, orientations, navigation aids and the obstructions in the vicinity of the aerodrome
  • 3. The potential to add a new runway and what lengths and orientations could be achieved
  • 4. Selection of a preferred replacement main runway, bearing in mind the need to minimise the environmental impact
  • 5. The potential locations for new apron and passenger terminal areas
  • 6. The related requirements for taxiway and surface access improvements
  • 7. Selection of a preferred apron and passenger terminal site
  • 8. The financial viability of the principle options
  • 9. Recommend options to go forward for public consultation

Two options were selected for consultation:

  • A. Retaining the existing runways and increasing the total permitted number of movements to 100,000 per year
  • B. Replace the existing main runway with a new 1,199m long runway and increasing the total permitted number of movements to 100,000 per year

The first represents a growth in the existing volumes of traffic, but not in its nature. The second provides a new longer and wider instrument runway, allowing the development of regional commercial air services.


Rejected Options

Top

All the other options that were rejected either:

  • I. Retained the present limits on aircraft operations and/or
  • II. Considered other alignments for a replacement main runway that had operational advantages, but, if adopted, would result in the overflying of a much larger built-up area

Retaining the existing restrictions on the number of movements, size of aircraft and operating hours would mean that the airport’s operations and income would remain virtually capped at existing levels.

While this remains an option, it is not a development option and therefore not one that would require public consultation or planning approval. Clearly such an option does nothing to secure the financial future of the airport and would be completely unattractive to investors.

What became clear from the technical studies was that construction of a new main runway is a prerequisite for the development of commercial air services and that a Code 2C 1,199m is the longest runway (within existing CAA rules) that could be built on the undeveloped land.

The construction and operating costs for such a replacement main runway would be much the same for all of the three possible alignments and this would also be true, irrespective of any limit on the number of movements.

Therefore, the retention of the 75,000 limit on the total number of annual runway movements would also mean that any commercial aircraft movements would have to displace existing general aviation traffic, which would result in significantly less income than if total numbers of movements were allowed to grow.

In considering the commercial viability of each of the options, the consultants advised the Councils that retaining the existing cap on the number of movements would be less likely to secure the financial viability of the airport or attract any private sector investment. In addition, retaining the existing Section 52 Agreement restrictions on aircraft size and operating hours would so limit the development of commercial air services, that this would also represent a "do nothing" option that could never financially support the cost of runway and terminal improvements.

All the options that included a new main runway also require the purchase of the undeveloped land to the west of the existing airfield, east of North Lancing and north of the railway. Even then, there is no prospect of building an 1,800m long Code 3C runway (as per SERAS), which is the minimum requirement for B737 and A320 jet operations. Thus short haul services by full-service, charter or no-frills carriers cannot develop at Shoreham. Reducing the length in stages down to 1,200m did not produce a solution, as the CAA now requires the application of all the clearances and obstacle surfaces for a new Code 3 runway down to that length.

Consequently, the only options considered further were for a Code 2 runway 1,199m long, as there is sufficient space on the extended site for such a runway and all the required clearance and safety areas.

Extending the existing surfaced runway to this length, or aligning a new runway through the relatively undeveloped gap immediately east of South Lancing (i.e. over the Happy Days Caravan Park) also proved impossible due to insufficient space and high ground to the north.

The alignments considered were 05/23 with a 4 degree approach, 06/24 with a 3.5 degree approach and 07/25 with a standard 3.0 degree approach. Even though it required the steepest angle of approach, the 05/23 alignment was selected as the preferred alignment as it resulted in the over-flying of the smallest built-up area.

  Top

Click on the maps for larger versions
  05/23
Runway Alignment 05/23

"Reproduced from the 1999 OS Ordnance Survey 1:25,000 scale map with the permission of the controller of HMSO
License Nr: AL 100019901"
  Top
06/24
Runway Alignment 06/24
"Reproduced from the 1999 OS Ordnance Survey 1:25,000 scale map with the permission of the controller of HMSO
License Nr: AL 100019901"
  Top
07/25
Runway Alignment 07/25
"Reproduced from the 1999 OS Ordnance Survey 1:25,000 scale map with the permission of the controller of HMSO
License Nr: AL 100019901"
Previous page    Next page Top

For job opportunities, click here.

RedAir
British Helicopter Advisory Board
Piper Parts (UK) Ltd.
Airport Operators Association
Charter Services
The Adur Economic Partnership
Flying Time
ORBIS - saving sight worldwide
Pipl
Padding